PTSC 03- PTSC02 Service Vessel Project

Table of contents

    On 10/10/2010, QME signed a contract with PTSC M&C for the flushing and pressure testing of hydraulic systems for two Stan Tug 3509 vessels (PTSC 02 and PTSC 03) newly built at the PTSC downstream port site.

    Project Overview:

    Hot oil flushing of the entire hydraulic system on board the vessel including the following systems:

    • Lube pipe System.

    • Winch ATF pipe system.

    • Crane Deck pipe system.

    • Steering system.

    • Kamfork System.

    • Tungger Winch System

     

    • Requirements:
    • Cleanliness of oil after cleaning reaches NAS 6-NAS7.
    • Flush station parameters: flow rate 1200l/min, Pressure 60bar.
    • Flush temperature from 50-65°C.
    • Test pipeline pressure to Max pressure: 450bar.

     

    Service equipment:

    • 01 60 KW station – 650l/min.
    • 01 44KW station – 580l/min.
    • 01 Pipeline pressure testing station – Max 700bar

    Human resources: Including 04 engineers and 01 commander

    Implementation time: 30 days

    Project completion date: 06/12/2010

    Investor: PTSC Quang Ngai Company.

    General contractor: DAMEN Netherlands.

    Construction contractor: PTSC M&C Floating Vehicles Department