The hydraulic pipeline flushing project for the Murjan 3 & Murjan 4 vessels has been successfully completed by the QME technical team. QME's pipeline flushing service is committed to completely removing contaminants, ensuring oil purity, and extending equipment lifespan for our customers.
On August 21st, QME performed hydraulic oil pipeline flushing for the Murjan 3 & Murjan 4 vessels.
Scope of work:
- Fluid flushing of DN200, SIZE 8'' pipelines using hot oil.
- Combined flushing of 2 stations with capacities (60Kw + 75Kw); Flow rate (850l/min + 1100l/min), pressure 20 bar, hot oil temperature 60-77°C.
- Running time: 12 hours per line.
- Fluidification to achieve NAS 5 cleanliness standard.
Execution time: 5 days
Main contractor: SAIGON SHIPYARD CO., LTD
Client: Greenbay
Project: Tugboat
Workers: QME Service Team
In just 5 days, the QME service team completed the project under the supervision of the main contractor, meeting all the contractor's requirements.
Some images of the Murjan 4 tugboat project:

The contractor Triyard is overseeing the construction