Details of Pipeline Flushing Service with Chemicals and Hydraulic Oil for 8 PTAS AMANAH H703-710 Ships

Table of contents

    On January 11, 2014, QME started the project "Chemical and hot oil washing for 8 PTAS AMANAH H703-710 ships" at STRATEGIC MARINE VIET NAM shipyard.

    Scope of work:

    • Step 1: Degreasing and neutralization
    • Step 2: Acid cleaning and neutralization
    • Step 3: Surface passivation
    • Step 4: Hot oil flushing to achieve cleanliness up to Class NAS6

    Service equipment: -Chemical system: 20m ³ / h -Chemical and water tanks -Special chemicals for degreasing and cleaning.

    Filter core:Hydac – Germany, 1300 lpm, 3/5 Micron

    Workers:QME Service Team

    Performance time:10 days

    Project completion date:21/01/2014

    Previously, another contractor had carried out this package for over 60 days. However, the results did not meet the investor's requirements.

    According to the expected time, QME would complete this project in 20 days, but the QME service team worked hard 24/24 and with skilled techniques, the QME service team completed the project ahead of schedule and met the investor's requirements.